Power Outages Hits Abuja, Kogi As Power Station Collapses

Power Outages

News

Power Outages Hits Abuja, Kogi As Power Station Collapses

Abuja DisCo will not be able to off-take power from the substation to its customers in Okene, Kabba, Ososo and Ikare

Abuja, Nigeria– Residents in various areas of Abuja and parts of Kogi State are currently experiencing power outages due to technical issues within the Abuja Electricity Distribution Company’s (AEDC) network.

The AEDC  informed its customers in Zamani Estate, Abacha Road Mararaba, Ruga Juli and other parts of Abuja on Tuesday, March 19, that a technical fault on 33kv feeder k6 from AT9 Karu Transmission Station was responsible for the power outage.

More Afrika Eyes News  BREAKING: Dariye, Nyame Released From Prison Months After Presidential Pardon

“The management of Abuja Electricity Distribution Plc wishes to notify its esteemed customers that there is currently a technical fault on 33kv feeder k6 from AT9 Karu Transmission Station, managed by the Transmission Company of Nigeria.

“The areas affected in Abuja are: Zamani Estate, Abacha Road Mararaba, Ruga Juli, Old Karu Road, Glory Estate and environs.”

More Afrika Eyes News  IEYDA Honours YPP Guber Candidate, Gobir

The AEDC disclosed that the TCN maintenance crew was working to ensure the supply of electricity to these areas was restored soon.

“The TCN had announced earlier that its maintenance crew would carry out planned maintenance on its TR3 45MVA and TR2 60MVA power transformers in its 132/33kV Okene Transmission Substation from Tuesday, March 19, to Wednesday, March 20, from 10 am to 03pm on each day.

More Afrika Eyes News   INEC To Receive N18 Billion For Bayelsa, Imo, Kogi Polls

“As a result, Abuja DisCo will not be able to off-take power from the substation to its customers in Okene, Kabba, Ososo and Ikare during the period of the maintenance.

“Kindly note that bulk power supply will be restored to Abuja DisCo immediately after maintenance work is completed.”